info iconPMP exam lasts 4h and has 200 questions
info iconUse acceleration to have extra 30m in reserve on exam

lock iconSchedule Management

Your sponsor and stakeholders want to be constantly informed on the project status. You are to report on many aspects of the project and you want to use the most appropriate tool for each case. Which of the following are generally illustrated better by bar charts than network diagrams?