PMP Exam Simulator

alarm icon
3h 50m 0s
info iconPMP exam lasts 230min and has 180 questions
info iconUse acceleration to have extra 30m in reserve on exam

lock iconCommunications Management

You are a project manager in a big company. Currently you are managing a project on the production of waterproof drones and there are 3 stakeholders you need to communicate with. Therefore, you have 6 channels of communication. A new stakeholder has just been added and you need to communicate with him as well. How many channels of communication do you have now?