lock iconCommunications Management

There have been changes to several deliverables. These changes have been documented in the project management plan. Also, they have been distributed accordingly to the communications management plan. One of the stakeholders is very surprised to hear about a documented change to a project deliverable. However, all the stakeholders had received the communication informing them of the change. The project manager should: