lock iconCommunications Management

The construction project you are managing is progressing according to the plan. Your team has developed a prototype which will be presented to the stakeholders for interaction and feedback. It will be an interactive process and the prototype will be modified many times until the requirements for the product are finalized. There is an upcoming project status meeting with the stakeholders. What should the project manager do during this meeting?