PMP Exam Simulator

alarm icon
4h 0m 0s
info iconPMP exam lasts 4h and has 200 questions
info iconUse acceleration to have extra 30m in reserve on exam

lock iconCost Management

You are managing a project to create editorial software. It must have built-in spelling and grammar checkers. Also, the software must find things like numerals in the middle of sentences, compound words and abbreviations that appear in different forms. The budget for the project is $5,000. You spent $4,000, however, only completed $2,200 worth of work. What do you currently expect the total project to cost?