PMP Exam Simulator

alarm icon
3h 50m 0s
info iconPMP exam lasts 230min and has 180 questions
info iconUse acceleration to have extra 30m in reserve on exam

lock iconCost Management

The project manager is overseeing the project to develop a printer that would use twice as less ink as a regular printer. Also, the functionality must include the feature to switch between ink and laser printing. The project manager is not sure whether they have enough funding to complete the project. He decides to use a technique of reconciling the expenditure of funds with the funding limits set for the project. In other words, he wants to check costs against the project's budget. As per the variance between the expenditure of funds and planned limit, he is trying to reschedule activities to level out the rates of expenditures. The technique the project manager is using is: