PMP Exam Simulator

alarm icon
4h 0m 0s
info iconPMP exam lasts 4h and has 200 questions
info iconUse acceleration to have extra 30m in reserve on exam

lock iconCost Management

You are working for the biggest supplier of training equipment for drivers that participate in auto racing. You have been assigned to oversee a project to manufacture a new piece of equipment designed to improve reaction, hand-eye coordination and stamina. During the forecasting analysis, you found out that the EAC = $270,000 and you are concerned by the fact that the SPI = 0.75 and CPI = 0.88. What is the most likely reason for this occurrence?