PMP Exam Simulator

alarm icon
4h 0m 0s
info iconPMP exam lasts 4h and has 200 questions
info iconUse acceleration to have extra 30m in reserve on exam

lock iconCost Management

You are a project manager for the billboard and digital screens company and you are overseeing a large project to install an iconic LED display on one of the buildings on Times Square, New York. The project will require special equipment that the company does not possess. You have had a meeting with a rental company representative and negotiated the terms for the rent of this equipment. The rental company will supply this equipment for $5,000 a month for the duration of the project. This is an example of: