lock iconCost Management

The project manager of the interior design firm requested to obtain historical information from previous similar projects. He wants to use it to determine the price per square foot of vinyl tile that will be used to cover the floor of the entire hotel which is 120,000 square foot. Which technique is the project manager using to create the estimate?