PMP Exam Simulator

alarm icon
4h 0m 0s
info iconPMP exam lasts 4h and has 200 questions
info iconUse acceleration to have extra 30m in reserve on exam

lock iconCost Management

David is a project manager with a lot of experience. He and the sponsor have different opinions on what estimating techniques to use. David believes that a form of expert judgement will do the best, and the sponsor wants to use analogous estimating. What is the best thing to do in this situation?