PMP Exam Simulator

alarm icon
3h 50m 0s
info iconPMP exam lasts 230min and has 180 questions
info iconUse acceleration to have extra 30m in reserve on exam

lock iconCost Management

The project manager and the project team are about to enter a meeting to determine project costs. The project manager has elected to use bottom-up estimating and will base his estimates on the WBS. Which one of the following is not an attribute of bottom-up estimating?