PMP Exam Simulator

alarm icon
3h 50m 0s
info iconPMP exam lasts 230min and has 180 questions
info iconUse acceleration to have extra 30m in reserve on exam

lock iconCost Management

A project manager who was overseeing a major construction project left your company. His project has been reassigned to you. The project has BAC = $50,400, PV = $35,000, cumulative AC = $30,000 and cumulative EV = $29,000. You need to perform a forecasting analysis and calculate the values for EAC, ETC, TCPI and VAC. Which of the following statements is FALSE?