PMP Exam Simulator
3h 50m 0s
Cost Management
The work on the WBS has been finished and the project schedule is almost finalized by the project manager and her team. Also, the project manager is planning to start working on the project budget. Which document will the project manager be using for planning, estimating, budgeting and controlling costs so that the project is completed within budget?