PMP Exam Simulator

alarm icon
3h 50m 0s
info iconPMP exam lasts 230min and has 180 questions
info iconUse acceleration to have extra 30m in reserve on exam

lock iconCost Management

You are managing a project to build one indoor and one outdoor swimming pools for the fitness center. While reviewing the progress of the project, you find out that EV = $60,000 and AC = $64,000. Also you've just been informed that several filtration systems have been damaged and it will cause a considerable cost overrun. The first thing to do for the project manager is: