Quality Management
Your team has been working on a project to design and produce new lenses for the action camera. It has been determined that the highest priority constraint on the project is cost. The team included random sampling of these lenses in their quality plan. The main factor is cost, however, the product must also meet high quality standard. Which of the following is NOT am example of the cost of nonconformance?