lock iconProcurement Management

Peter is a project manager at a GPS systems company, leading a project to develop an innovative GPS system for vehicles. He has been informed that a few regulations related to how the products are manufactured will change in three months. While planning for work to change some design and production processes, Peter determines that he will need to work with external organizations. What type of contract should he use to have enough help to audit invoices?