PMP Exam Simulator

alarm icon
3h 50m 0s
info iconPMP exam lasts 230min and has 180 questions
info iconUse acceleration to have extra 30m in reserve on exam

lock iconScope Management

Luis has been managing a seven-month project. He had meetings with the project stakeholders once every two weeks and now, after six and a half months of work, the project is on budget and schedule. However, the stakeholders are not happy with the deliverables and it will delay the project completion by one month. What process could have prevented this situation?