Frank has been successfully managing a project. A few weeks ago he had a meeting with the buyer and was requested to report periodically on the progress of the project. These reports include analysis of the work that has been accomplished according to the plan, funds that have been spent, the accepted deliverables and evaluation of the risk events that have taken place. What represents the estimated value of the work actually accomplished?