You are managing the construction project to build a hotel. It's important that the electric should always come after the plumbing, in fact, much of the actual work for the electricity doesn't usually happen until later. Your team members know that they cannot run an electrical line on a construction site that has not dried in. However, you've been informed that the electrical team showed up even though the plumbing work has not been completed yet. The electrical team is not sure when they are supposed to start the work. Which one of the following is contributing to the issue the most?