lock iconIntegration Management

One of the project managers in your company resigned and the project he was managing has been reassigned to you, right in the middle of executing. You notice that many new change requests are coming from your key stakeholders, customers and even from your manager. You are worried that changes will increase the cost and time of the project. You are not sure about how to process these incoming change requests. What should you refer to for help in this situation?