PMP Exam Simulator

alarm icon
3h 50m 0s
info iconPMP exam lasts 230min and has 180 questions
info iconUse acceleration to have extra 30m in reserve on exam

lock iconIntegration Management

The project manager has successfully completed all the work on pharmaceutical project. The stakeholders confirmed their final acceptance of the project. Now the project manager is meeting with his team to update the organizational process assets with the knowledge gained about the project to help with future projects. What should the project manager do next after the lessons learned is completed?