PMP Exam Simulator

alarm icon
4h 0m 0s
info iconPMP exam lasts 4h and has 200 questions
info iconUse acceleration to have extra 30m in reserve on exam

lock iconIntegration Management

A project manager has been assigned to a project in a field where he has no experience. He delegates the processes of Develop Schedule, Estimate Costs, Define Activities and Estimate Activity Resources to various project team members. The project manager serves as a coordinator of activities. What are likely results of this approach?