lock iconIntegration Management

The project was going well when suddenly changes to the project came from multiple stakeholders. After all the changes were determined, the project manager spent time with the stakeholders to find out why there were changes and to discover any more. Some time passed and the project work quieted down. One of the team members mentioned to the project manager that he added functionality to a product of the project. He also said that it did not affect schedule, cost or quality. What is the first thing the project manager should do?