PMP Exam Simulator

alarm icon
4h 0m 0s
info iconPMP exam lasts 4h and has 200 questions
info iconUse acceleration to have extra 30m in reserve on exam

lock iconSchedule Management

A design team member believes that his work is too creative to provide the project manager with a fixed single estimate for the activity. He and the project manager decide to use the average labor hours, based on previous similar projects, in order to develop a prototype. This is an example of: