PMP Exam Simulator

alarm icon
3h 50m 0s
info iconPMP exam lasts 230min and has 180 questions
info iconUse acceleration to have extra 30m in reserve on exam

lock iconProcurement Management

You are managing a software project to develop an application that uses image recognition to identify scanned artworks and provide people with additional information about them. At the moment you are in the Control Procurements process. You want to identify performance progress or failures and identify the areas where performance must be improved. You've scheduled a meeting with your seller to inspect the seller's progress to deliver project scope and quality within cost and schedule as compared to the contract. You are performing: