lock iconProcurement Management

You are managing a project to develop an extremely lightweight and small device to measure radiation. You disagree with the customer on interpretation of one clause in the contract. A change request has been submitted by the customer recently. She wants a new deliverable to be implemented as per the contract immediately. In your opinion, the demand is unrealistic. To resolve the issue you should: