lock iconProcurement Management

You are managing a construction project of a modern flood control system that would protect communities from potentially catastrophic flooding and loss of life and property. You signed a contract with a vendor to deliver important equipment to the construction sight. Now, the vendor informs you that he is not able to deliver the equipment on the agreed due date. The vendor has to wait for two months longer before he can deliver the equipment. This delay is going to cause a major problem to your project.Your team can find another vendor who can deliver the equipment for a small increase in costs. The best thing for you do in this situation is to: