There have been complications on the project and negotiations have become difficult. Party 1 makes notes that both parties sign. After the work is done, Party 2 says they don't have to provide a service they agreed to during the negotiations. And the reason for it is that it wasn't included in the subsequent contract. Is Party 2 right?