PMP Exam Simulator
3h 50m 0s
Procurement Management
In your organization, there are many rules regarding the procurement process. All correspondence between you and the vendors must be recorded and stored as part of the procurement records management system. These rules also provide instructions for the project’s procurement document packages from procurement planning through contract closure. Which statement is true about procurement document packages?