PMP Exam Simulator

alarm icon
3h 50m 0s
info iconPMP exam lasts 230min and has 180 questions
info iconUse acceleration to have extra 30m in reserve on exam

lock iconProject Management Processes

You've been managing projects for a construction company for more than 10 years. You know that in multiphase projects, the projects are planned during developing phases that are performed sequentially. This is done to get the desired result and to ensure control of the project. Sometimes, while managing some projects, you had to accelerate the project life cycle by overlapping project phases. All of the following statements are correct about this overlapping relationship EXCEPT: