You are managing a telecom project to construct new telecommunications towers, reinforce or modify existing towers, install lines and antennas and perform maintenance on existing structures. While digging for a new tower, some artifacts have been discovered. You realize that these artifacts may have some archaeological value. What should you do in this situation?