Project Management Processes
The WBS and WBS dictionary have been completed, and the project team started working on identifying risks. The sponsor contacts the project manager and requests the responsibility assignment matrix be issued. The project has a budget of $350,000 and is taking place in 5 countries using 20 human resources. The project manager has managed many similar projects before, and there is little risk expected for the project. The next thing to do would be: