info iconPMP exam lasts 4h and has 200 questions
info iconUse acceleration to have extra 30m in reserve on exam

lock iconProject Management Processes

You have been assigned to oversee a project to create the lightest type of plastic possible. You came up with a few orders of magnitude estimates, high-level risks, constraints and assumptions for the project. Which project management process group are you in?