lock iconProject Management Responsibility

You are managing a project to renovate a hospital. After the renovation is completed, it's planned to build additional premises near the main hospital building. This morning you had a meeting with the sponsor to discuss the project schedule. Both of you agreed that the project is behind schedule and that it's impossible to meet the deadline. The sponsor asked you not to inform the customer about that fact in the next status meeting which will take place in two days. What should you, as the project manager, do in this situation?