Project Management Responsibility
The project manager of a software development company has been working on finalizing the weekly project status and progress reports. He discovers a few deliverables that are not completed but have been reported as completed. Besides, the team members reported the days spent on the activities incorrectly. As a result of these incorrect estimates, the project statistics and updates become unrealistic. What should the project manager do first in this situation?