lock iconProject Management Responsibility

Due to limited resources, your company cannot work on all the potential projects available. You are a member of the proposal evaluation team responsible for evaluating potential projects and awarding contracts to the best vendors. Your opinion is very valued because you have experience in comparing potential projects and finding out the best one with the most value based on the project triggers and benefit measurement methods. During the review of potential vendors, you notice that one of the participants in the bidding process is a good friend of yours. You know that your friend is a real expert and you believe that if your friend is awarded the contact, the project will be greatly benefited. The best course of action in this situation would be: