PMP Exam Simulator

alarm icon
3h 50m 0s
info iconPMP exam lasts 230min and has 180 questions
info iconUse acceleration to have extra 30m in reserve on exam

lock iconProject Management Responsibility

You have just been assigned as the project manager for a project to update a call center and customer support for a corporation. You were asked by the sponsor to complete the project in five months and within $100.000. You realize that both time and cost estimation from higher management is impractical. After performing your own estimation, you conclude that the project will take about seven months and will cost at least $120.00. The project sponsor informs you that in case you don't agree with his time and cost estimations, they have another project manager to consider for the position. What should you do as the project manager?