PMP Exam Simulator

alarm icon
4h 0m 0s
info iconPMP exam lasts 4h and has 200 questions
info iconUse acceleration to have extra 30m in reserve on exam

lock iconProject Management Responsibility

You have been assigned to a project that will involve team members from five different countries. On the one hand, the project has strong support from senior management, on the other hand, this type of project is new to everyone on the team. In order to make sure the cultural differences don't interfere with the project, the project manager has to: