lock iconProject Management Responsibility

You are managing the project that must be completed within four months. After two months, the schedule has begun to slip. Now, the project is one week behind schedule. You think you can make some corrective actions and recover the lost time over the next month to get the project back on schedule for its completion date. Management requires weekly status reports on cost and schedule. What should you do?