lock iconProject Management Terms

The project manager has identified a few positive and a few negative stakeholders for a construction project. The project manager and the project team have been regularly meeting with the positive stakeholders but have not met with the negative stakeholders. The Chief Project Office from the PMO wants the project manager to meet with the negative stakeholders as soon as possible. What type of PMO is described?