lock iconProject Management Terms

The project you are managing has been reassigned to you after the previous project manager left the company. You see that the project was poorly managed before and now it's in a very poor condition. You decide to develop specific work plans for each of the 20 work packages. However, you realize that the plan would help each phase, but would not control the integration of those phases into one whole. Also, there are no defined project deliverables. The situation is calling for you to organize the project ASAP. The best thing for you to do is: