lock iconProject Management Terms

The project manager identified scope, cost, time, quality, risk, resources, communications and customer satisfaction to be major contraints on his project. He is extremely worried about these constraints as they provide a framework for understanding trade-offs in managing competing project requirements. What is the right priority order of these constraints?