PMP Exam Simulator

alarm icon
3h 50m 0s
info iconPMP exam lasts 230min and has 180 questions
info iconUse acceleration to have extra 30m in reserve on exam

lock iconScope Management

You are managing a museum renewal project. The project appears to have some missing scope. Your understanding of the scope was that the floors were to be refinished and the ceilings coated. One of the construction workers has come to you to ask why there is no mention of painting the new hanging system on the walls. He also wants no know if there are any additional lightning work packages in the project. You have seen one hall where the work is completed, with the new hanging system on the walls painted. What do you think most likely caused the misinterpretation of the project scope statement?