PMP Exam Simulator

alarm icon
4h 0m 0s
info iconPMP exam lasts 4h and has 200 questions
info iconUse acceleration to have extra 30m in reserve on exam

lock iconQuality Management

The project manager is in the Control Quality process of the project to renovate the Botanical Garden fence. The fence has been installed and the project manager has to inspect it to ensure that it's high enough, that it's not too close to the plants and trees, that it covers all the perimeter of the Garden etc. Which of the following is FALSE about the fundamental functionality of the Control Quality process?