3h 50m 0s
info iconPMP exam lasts 230min and has 180 questions
info iconUse acceleration to have extra 30m in reserve on exam

lock iconQuality Management

You are working for a company that produces camera equipment. Recently, there has been a quality problem with one of the manufacturing processes used to create lenses. Only half of the manufactured lenses have been within the control limits set by the Quality Assurance team. You, as the project manager, need to review the process activities to find out where the process went wrong. To gather required information you will use: