lock iconQuality Management

You are the project manager of the project which is part of the program to construct the tallest building in town. Another program manager has required that you document any variances to costs, schedule, scope and quality expectations as part of the program governance. You believe that your project team now has an internal failure cost that needs to be documented. Which of the following is an example of internal failure cost?