PMP Exam Simulator

alarm icon
3h 50m 0s
info iconPMP exam lasts 230min and has 180 questions
info iconUse acceleration to have extra 30m in reserve on exam

lock iconQuality Management

You are the project manager of the project which is part of the program to construct the tallest building in town. Another program manager has required that you document any variances to costs, schedule, scope and quality expectations as part of the program governance. You believe that your project team now has an internal failure cost that needs to be documented. Which of the following is an example of internal failure cost?