PMP Exam Simulator

alarm icon
3h 50m 0s
info iconPMP exam lasts 230min and has 180 questions
info iconUse acceleration to have extra 30m in reserve on exam

lock iconQuality Management

The project manager is working with the team to identify errors in the project deliverables. As part of this process, they have to calculate the cost of the error, materials, time and the cost to redo the work. In this situation, in regards to quality management, which of the following is not an attribute of failure costs that the project manager will need to consider?