info iconPMP exam lasts 4h and has 200 questions
info iconUse acceleration to have extra 30m in reserve on exam

lock iconQuality Management

You are in the middle of the project on a new race car model. The engines have already been assembled from a bare block and the frame has been constructed from steel tubing. Now a senior manager comes to you and says that he is concerned that the project might not meet quality standards. What should you do in this situation?