Resource Management
You are managing a project to merge two existing applications into one for an accounting company. You need two additional resources from different functional areas. Today you had a meeting to discuss this issue, however, the functional manager was reluctant to assign her resources to your project. You tried to make the functional manager change her mind by using your association with a high-level executive for leverage. By doing this, you used which one of the following forms of power?