Resource Management
One of the team members just told you that he has a problem: the deliverable he is currently working on must be shipped today, otherwise there will be a project breach. At the same time, a stakeholder wants to talk to you regarding a disagreement with another stakeholder on whether a deliverable meets the acceptance criteria. You reply to the stakeholder that you cannot deal with it right now. You used the following technique: